Contractors & ConstructionManagers Since 1989.

Level, Grade and Remove Rock

New Construction. Builder left pit/run backfill as finish grade for yard. Picked rocks w/rock rake. Minimized top-soil hauling to 45 tons (3 truck loads) to cover 2+ acres. Dialed in finish grade. Fencing/Sprinklers and repaired grade to prep for hydroseed in back yard and sod in front yard.

Sewer Taps for Multi-Unit Residential Complex

This particular sewer connect included a four-building apartment complex. Engineering called for a single 4″ line from each building. In order to meet code, we had to excavate a large portion of the sewer mainline (City of Driggs). Groundwater was a problem that required us to perform this installation in late summer and required the use of pumps to keep the trench clear.

Stormwater Management System and Parking Lot in Victor Idaho

This project included the excavation and installation of a stormwater management system in Victor Idaho. This stormwater management system used the R-tank style retention tank. This installation included the installation of two man-holes, inspection ports, and approximately 300 feet of 6-inch drain line.

Repair Lawn After Septic Failure

Customer had a septic system failure. Another contractor replaced the drainfield, but we were called in after that replacement left unstable/uneven ground. We stripped the old sod, leveled the ground and blended the new sod in. After the initial repairs, the customer asked me to lay sod over the decommissioned garden.

Excavate Septic Test Hole

Excavated test-hole for septic permitting. Arranged with local resources for inspection.

Relocate Water Meter Pit & Fiber

This project required us to relocate the water meter and fiber to make room for the parking lot. We removed the 2″ meter pit and replaced with a 1″ line for irrigation.

Foundation Excavation for Multi-Unit Residential Complex in Victor

This project included the excavation of a crawl-space foundation in Victor, Idaho.

Complex Septic Install

This project included the installation of a complex septic system. This system utilized two tanks, with a 1.25″ pressureized discharge that crossed a county road to the drain field location.

Build Mountain Road

Customer needed a construction-access road (and foundation for permanent road) constructed to his property. Cut away hundreds of yards of overburden. Surveyed grade to maintain <10% grade. Installed 12-inches of pit-run. Installed drainage ditches.

Build Rock Retaining Walls

New Construction. Haul in and use existing lava/basalt boulders to complete over 200 linear ft of rock wall.