- Removing topsoil, preparing for foundation excavation
- Grading the lot
- Working on excavation
- Completed excavation, ready for forms
- Completed excavation, ready for forms
- Completed excavation, ready for forms
- Backfilling the foundation
- Compaction
- Backfill
- Compaction
- Backfilling the foundation
- Bringing the interior floor to grade
- Working on interior grade
- Finished foundation with interior grade ready for concrete
- Finished foundation with interior grade ready for concrete
- We unloaded and stacked the steel for the building
Project Description
Client: H. Vogel
Location: Driggs, ID
Year Completed: 2022
The Challenges
Excavate a foundation for an indoor pickle-ball court. Backfill and compaction after concrete work.